New Orleans Airport Finishes $27M Runway Work and Starts 380-Spot Parking Project
The Louis Armstrong New Orleans International Airport completed major infrastructure upgrades ahead of the holiday travel season and broke ground on new parking lots this month.
By Robert Ward ·

The Louis Armstrong New Orleans International Airport has finished a $27.1 million renovation of one of its runways and begun construction on 380 new parking spaces. City and airport officials released details on these two projects earlier this month, noting they address safety and traveler convenience at the facility.
The runway work concluded just before the Thanksgiving travel period. The project took about nine months to complete and involved reconstructing the center panels across the entire 7,000-foot runway. Crews also installed new electrical systems and replaced the lighting embedded in the pavement that guides pilots at night. Funding for this specific renovation came from the Federal Aviation Administration’s Airport Improvement Program.
With the runway complete, workers are now moving on to a separate $5.6 million project to add parking capacity. The plan includes two new overflow surface lots located within walking distance of the terminal. One lot will sit east of the short-term garage, and the other will be east of the long-term garage.
Kevin Dolliole, the director of aviation, stated that growing demand for parking makes this an important investment in reliability. He described parking as one of the first and last touch points of a passenger’s trip, adding that the goal is to keep that experience simple and stress-free.
Officials expect construction on the two new lots to finish by April 2027. The airport currently offers more than 10,000 parking spaces across its short-term, long-term, and economy garages, as well as a surface lot and valet service.
James Williams, chair of the New Orleans Aviation Board, said in a statement that taking care of existing infrastructure is just as important as building what comes next. The current projects are part of a larger master plan for the airport that includes expanding the ticket lobby, security checkpoint, and baggage claim areas. The plan also calls for more gates and a new parking garage.
Mayor Helena Moreno said the city is using federal investments to strengthen the safety and efficiency of the airport. She noted that a modern transportation system supports economic growth and serves the community for years to come.
More Business · Consumer Alerts · Report a business · Got a Story?






