Downtown Fort Worth is on track to generate roughly $2.9 billion in economic activity by 2030, according to a forecast presented to the Downtown Tax Increment Reinvestment Zone board. The projection relies heavily on upcoming improvements to the convention center, the construction of new hotel rooms, and the expansion of Texas A&M University's presence in the city. Andy Taft, president of Downtown Fort Worth Inc., delivered the estimates on Nov. 4.
The $2.9 billion figure breaks down into three main categories. Taft attributed $881 million of that total to the convention center and its associated projects. Hotels are expected to account for $693 million, while development linked to Texas A&M represents $519.5 million. Taft noted that the university's long-term financial impact could exceed these initial estimates as the Switchyard Innovation District matures.
"What we know is coming up is the Switchyard district, which will be more than just Texas A&M," Taft said. He warned that the area will likely require additional public investment in infrastructure. Butler Place, located outside the tax increment reinvestment district, is a prime example. Taft stated that the neighborhood will eventually need significant economic development assistance and infrastructure upgrades.
Taft also highlighted several other areas that support downtown growth. These include Panther Island, the Near Southside, and the West 7th Urban Village. A planned rail connection to the hospital district is also expected to contribute. He recommended that the board keep both the Downtown and Lancaster tax increment reinvestment districts active. Taft suggested aligning the development, financing plans, and governing boards for these projects.
Infrastructure work is progressing in the core area. Design plans for Weatherford and Belknap streets have reached the 90% stage. Four intersections near the courthouse are also at the 90% design level. Heritage Park is moving into the 60% design phase, with $1 million already allocated for the project.
The board also approved the fiscal year 2027 budget. Matt Beard, director of the Fort Worth Public Improvement Districts, reported that revenue is projected at about $5.1 million. This figure is down approximately $8,500 from the previous year. Expenses are set to climb from $237,500 to about $1.9 million. Beard identified the southeast quadrant parking project as the primary driver for the increased spending.
The fund balance for the downtown tax increment reinvestment district is expected to grow steadily. Beard said the balance will rise from about $28.4 million in 2027 to $40.9 million by 2031.